§ 46-114. Permanent trench covering.
Latest version.
The final surface shall take place before the construction year ends, no later than November 15, and all cuts made in the off-season, November 15 to April 15, shall be completed before June 15 of the following construction season, unless prior arrangements have been made with the director of public works and/or his/her designee.
(Ord. No. 17-2003, § 15, 10-27-2003)